At its first regular meeting of August 2025, the school board received an update on district construction and site projects, including completion timelines and weather-related delays. Superintendent Schaeders told the board the high-school 200 hallway renovation is finished and ready for use; the district’s team wellness clinic is essentially ready, with a few punch-list items remaining; and most middle-school work is complete but playgrounds were not finished in time for the start of school because of recent weather. A final walkthrough was scheduled for Thursday, Aug. 14, and staff said the playground and related items were expected to be ready Monday, Aug. 18. The board did not take formal action on the project update; the item was presented as information. The superintendent also outlined the larger planned high-school renovation that she said will focus on a northeast math and special‑education area, the science department, corridors and the cafeteria; she said the work is targeted to take about one to two years. Board members asked questions during the update and were given projected timelines but no binding schedule or funding action was recorded in the meeting minutes. The update included a note that smaller site items and parking-lot work will be scheduled as part of a 2–3 year planning process the superintendent described as a district priority. Implementation and scheduling details — including funding sources and contract awards — were not specified at the meeting.