County engineer details resurfacing, bridge schedules; Marshallville bridge demolition set for next week
Summary
County Engineer reported resurfacing schedules for multiple roads, encasement work on Avalon Canal Bridge nearing completion, and demolition of Marshallville Road Bridge scheduled for next week with a prefabricated replacement expected in early November.
Get email alerts on the Roads And Bridges Projects topic
No spam. Unsubscribe anytime.
At the Sept. 9 meeting the county engineer reported a series of road and bridge projects across Cape May County, including start dates for resurfacing and timelines for bridge replacement work. Key updates: Resurfacing of Mill Road in Upper Township was slated to begin the day after the meeting and expected to take one week, followed by a week for guardrail replacement and driveway reconstructions. In Lower Township, resurfacing of Townbank Road and Phase 2 of Fishing Creek Road was tentatively scheduled for the week of Sept. 15. Other projects named were Magnolia Drive and Phase 2 of East Creek Mill Road and Seashore Road resurfacing. Final paving at the Park & Zoo was scheduled to begin Oct. 27. Bridge work: Encasement work on the Avalon Canal Bridge was reported to be near completion in approximately two weeks. Demolition of Marshallville Road Bridge in Upper Township was scheduled for next week; the replacement bridge is being prefabricated off site and expected to be delivered in early November. Middle Thorofare Bridge: Commissioner Morey asked about the timeline for the Middle Thorofare Bridge; the engineer said the project is in preliminary engineering and permitting, which will last roughly two years, followed by a final engineering phase estimated at 1.5 to 2 years. Public safety and enforcement: Director Desiderio thanked Middle Township’s mayor and police chief for stepped-up enforcement on Avalon Boulevard; the engineer said an RFP related to the Avalon Boulevard issue was expected to be posted within the next week. What this means: Several short-term resurfacing projects are imminent, and longer-term bridge projects — notably Middle Thorofare — are in early design and permitting stages and will likely take several years to complete.