Commission recommends similar conditions for Hiddle Township solar site, adds east screening and cover-crop requirement
Summary
For petition 2529 S in Hiddle Township, the commission recommended conditions similar to Elm Grove — perimeter fencing, vegetative buffers and contact signage — and added an east-side vegetative screen plus a requirement for a cover crop before construction to limit dust and soil tracking.
Get email alerts on the Solar Development topic
No spam. Unsubscribe anytime.
Tazewell County Planning Commission members recommended approval of petition 2529 S for a solar facility in Hiddle Township with site-management and screening conditions similar to those attached to the Elm Grove case, and added an east-side screen and a pre-construction cover crop.
Commissioners reviewed Exhibit A and the site map; the commission discussed vegetative screening on the north against Third Street and additional screening on the east along Armington Road. The Tri-County planner’s report and testimony were referenced as supporting documents.
Commissioners said they wanted the same standard conditions used on prior solar petitions — perimeter fence, vegetative buffer immediately outside the fence, and contact information posted at the entrance — and specifically recommended adding vegetative screening on the east side and a cover crop prior to construction to reduce wind-blown dust and limit soil tracking to nearby homes.
Commissioner Coopy moved the petition onto the floor; Commissioner Bear seconded. The Tri-County planner’s findings of fact were read as positive and approved after a motion by Commissioner Lastly and a second by Commissioner Miller. The commission then voted in favor of recommending the petition; roll-call names recorded in the transcript include Mayor (recorded prompt), Lastly, Miller and Coopy with affirmative responses.
Commissioners emphasized these are recommendations to the county board, which retains final authority over rezoning and permits. The commission’s additional screening and cover-crop conditions will be included in the recommendation to the county board and in any permit review.