Council approves change orders for Phase 2 stormwater project to replace and lower water lines

5810828 · September 10, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved change orders to replace and lower multiple water lines to accommodate box culverts; the work includes upsizing a segment to 8-inch and creating a loop connection; cost not to exceed $180,790 from the utility fund.

Park City Council approved change orders Sept. 9 for the Phase 2 stormwater drainage project that require lowering and replacing several water lines where new box culverts will be installed.

Staff outlined specific locations: East Parkview near Judson, Hartford near Ashford, and Mobile Drive. The proposal would replace and lower water lines at Parkview and Hartford with 4-inch lines and upsize the Mobile Drive segment from 4-inch to 8-inch, creating a loop connection to an existing 8-inch main on Connolly Court.

The nut graf: upsizing the Mobile Drive segment provides system resiliency by creating a loop and replaces aging infrastructure; the work is consistent with the city’s annual water-line replacement program and is proposed to be paid from the utility fund.

Total projected contract cost for the work was presented as $145,590; staff recommended approval of a change order not to exceed $180,790 to be paid from the utility fund. Terry Osborne moved to approve the change order; Jim Schrader seconded and the council voted 7-0.

Staff said the upsized 8-inch connection will eliminate a dead end and improve water coverage. The council approved the funding transfer from the utility fund’s CIP/CEF improvement accounts to cover the unbudgeted additional costs.