Board approves Pay Estimate No. 1 for Cutler Park restroom renovation: $82,180.43 requested
Summary
The board approved Pay Estimate No. 1 for Cutler Park restroom renovation, representing completed work July–August; the requested payment after retainage is $82,180.43 and the adjusted contract total is $178,500.
Get email alerts on the Parks And Recreation Facilities topic
No spam. Unsubscribe anytime.
The Kokomo Board of Public Works and Safety approved Pay Estimate No. 1 for the Cutler Park restroom renovation at its Sept. 3 meeting. Darren Metz, traffic systems manager, presented the estimate and quantities agreed between the contractor and the engineering department.
Metz said pay estimate number 1 represents construction quantities completed from July 2025 through Aug. 20, 2025. The gross amount listed for payment number 1 was $84,722.10; after retainage the requested payment is $82,180.43. The original contract amount was $162,975; contract modification number 1 increased the adjusted contract amount to $178,500. The board voted to approve the pay estimate.
The meeting record contains inconsistent contractor naming: the item was attributed to Hearne Construction Inc. earlier in the presentation and the approval line references Hunter Construction Inc. The board did not resolve that discrepancy during the meeting; staff follow-up is implied but not recorded.