Council approves $5.01 million guaranteed maximum price for King Municipal Operations Center
Summary
The Angleton City Council approved a guaranteed maximum price of $5,005,919.63 and awarded the construction phase to the city’s construction manager at‑risk; the contract includes a 5% contingency and an 80/20 savings split.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
Angleton — The Angleton City Council approved a guaranteed maximum price (GMP) of $5,005,919.63 for the King Municipal Operations Center and awarded the construction phase to the city’s construction manager at‑risk on May 27, 2025.
The vote followed a presentation from project architect Brent Bowles and Jason Hoag, who identified himself as president of the construction manager. Hoag said the GMP package includes a 5% total contingency — split as 2.5% for the construction manager and 2.5% for owner contingency — and several allowances. "Anything that's left over ... you guys will get 80% of that," Hoag said, describing the previously agreed 80/20 savings split for buyouts and subcontractor savings.
Why it matters: Councilors said approving the GMP allows the city to lock in subcontractor pricing and move into procurement and permitting. Hoag urged approval by June 2 to secure subcontractor pricing and begin procurement and permitting, saying early award would let the team "lock in material pricing" and start procurement so the project can begin work once permits are issued.
Key details: The preconstruction phase included about 90 subcontractor bids, with the construction manager expecting to manage roughly 25 subcontractors during construction. Hoag estimated a 12‑month construction schedule, possibly 11 months depending on demo phasing. Council members and staff discussed logistics for demolishing the existing building and using the annex to stage work to speed construction.
Formal action: Mayor Pro Tem Townsend moved approval of the AIA A133 Exhibit A document package establishing the GMP in the amount of $5,005,919.63; Councilman Sarton seconded. The council approved the motion by voice vote.
Next steps: With the GMP approved, the construction manager will proceed with procurement of subcontractors, lock pricing where possible, submit for permits and begin phased demolition and construction according to the approved schedule. The council and staff said they expect to track buyout savings and report any major changes back to council.