District receives Phase 2 construction update; contingency funds remain, Harmony Hill paving rebid

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Turner Construction and district staff told the Board of Education that Phase 2 work is on track for opening day, with remaining contract contingencies and a Harmony Hill paving rebid due later this month. Board members were told access to buildings is not in jeopardy.

Turner Construction gave the Cohoes City School District Board of Education an update on Phase 2 of the district capital project, and the district's facilities director summarized remaining work and contingency funds.

The presentation, given at the Aug. 13 board meeting at Cohoes Middle School, covered exterior door work, abatement in several rooms, drainage and curb installation, striping, and other site work. District staff and Turner representatives said the remaining items are scheduled to finish before school opens and that they are not expecting the construction to prevent building access on opening day.

The district reported a remaining construction pot described in the presentation as "174.5 left over" (units not specified in the transcript), which the presenter said represents about 14% of the original contingency/allowance pool; of the funds still available for work, about 6% was described as contingency for unplanned needs. The presenter characterized that balance as within normal expectations for this stage of the project; the transcript did not specify whether the dollar figure is thousands or millions, so units are not stated here.

Board members asked about Harmony Hill's parking and drop-off congestion. Staff said a parking lot bid is out for rebid and is due on the 20th; if the bid process produces a vendor, paving would follow. The district said it had put the Harmony Hill lot into the work scope because contingency remained and the site change was a relatively straightforward add.

Other specific items noted in the update included replacement or adjustment of exterior panels and thresholds at Abraham Lansing (as described in the presentation), scheduled abatement in Room 326 and Room 4, and planned installation of a large floor assembly and completion of the fire alarm system and punch-list items. Staff also reported work this week on drainage and curb installations near the kitchen and maintenance areas.

No formal action was taken on construction contracts at the meeting; routine contract and bid items were on the consent agenda the board moved to adopt (see Actions).