Board authorizes direct pre-purchase of rail materials for 119-mile segment, approves $507.1M state-funded notice to proceed
Summary
The board approved staff's request to pre-purchase long-lead rail materials for the first 119-mile construction segment (not-to-exceed $507.1 million, state funded) and authorized future optional notices to proceed; board amended the resolution to require reporting back on any substantive small-business policy changes.
The California High-Speed Rail Authority board approved a staff request to pre-purchase long-lead rail materials for the authority's current 119-mile construction segment, authorizing a not-to-exceed budget of $507.1 million funded 100 percent by the state for Notice to Proceed 1. The contracts will cover rail (UIC 60), concrete ties, overhead contact system components and poles, fiber-optic cable and European-standard ballast, staff said.
Emily Morrison, the authority's chief of contracting, told the board the procurement is intended to reduce lead times and lower overall construction costs by buying certain…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat