Superintendent: Duval project advancing; trusses arrived and paving preconstruction to begin
Summary
Superintendent reported progress on the Duval construction project and other site work: trusses arrived for a front entrance, gas pump foundation to be poured and a preconstruction meeting for paving is forthcoming; the superintendent proposed a mid‑September site tour.
Get email alerts on the Facilities Construction topic
No spam. Unsubscribe anytime.
Superintendent Barnett updated the board Tuesday on ongoing construction at district facilities, saying the Duval project is progressing and “looking pretty schooly.” He told the board that trusses for the front entrance arrived and that crew work on forms and rebar for a gas‑pump foundation was expected to lead to a concrete pour the following day.
Barnett said he spoke with the clerk of the works and the project manager and proposed scheduling a site tour for the board, likely a Friday in mid‑September, when the project manager can provide a walkthrough. He also said the district will hold a preconstruction meeting on paving projects soon to keep that work moving.
The nut graf: the superintendent reported routine construction milestones and logistics and told the board staff would arrange a site tour and preconstruction meetings to brief board members on schedules and next steps.
No contract actions or new project approvals were presented at the meeting; the superintendent described the current schedule and expected forthcoming work steps.