Council approves rezoning for 332-acre Inland Port parcel; wetlands to be protected

5793660 · September 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved rezoning 332.48 acres off Burmester Road from MU-40 to MG (general manufacturing) within the Inland Port area, with about 60% of the site identified as wetlands and mitigation planned; a traffic signal is recommended by 2030 at I-80 and Burmester.

The Tooele County Council approved Ordinance 2025-12 on Sept. 2 to rezone 332.48 acres located off Burmester Road from MU-40 (multiple use, 40-acre minimum) to MG (manufacturing general) within the Inland Port project area. Rochelle (staff) told the council the applicant’s land includes roughly 60% wetlands that the applicant will protect through either a wetland mitigation bank or a mitigation project; staff will return to the council with the mitigation plan once the applicant chooses.

Rochelle told the council a traffic study recommended installation of a traffic signal at the I-80/Burmester intersection by about 2030 to serve projected truck traffic at full build-out; she said the study projects the majority of heavy truck traffic would go directly to I-80 and not into adjacent residential areas. Planning commission made a unanimous favorable recommendation on the rezoning.

Council action: Councilman Hoffman moved to approve the rezoning, with a second from Councilman Wardle. The motion passed unanimously with the council members present.

Discussion and conditions: Rochelle said wetlands would be protected and that the applicant would bring a mitigation plan for council review. The council heard resident concern (Miss Durfee) about traffic; staff noted full build-out traffic is projected for 2030–2050 with most heavy truck traffic going to I-80.

Why it matters: Rezoning places a large parcel inside the county’s Inland Port area into a manufacturing designation and triggers mitigation and traffic improvements as the site develops. The county will review wetland mitigation plans and future permits as the project proceeds.