Council approves $749,000 contract for Skywalk Bridge 3 repairs; resident asks for completion date
Summary
Council designated Hildreth Construction Services LLC as the lowest responsive bidder for Skywalk Bridge 3 repairs at $749,000; a resident asked about the target completion date, which a city official gave as Jan. 21, 2026.
Get email alerts on the Infrastructure Skywalk Repair topic
No spam. Unsubscribe anytime.
The Des Moines City Council approved plans, specifications and contract documents Sept. 8 for repairs to Skywalk Bridge 3 and designated Hildreth Construction Services LLC (Mark R. Hildreth, owner) as the lowest responsive, responsible bidder for $749,000 (Council communication No. 25-341). The council moved, seconded and approved the action by a 7-0 vote. During the public hearings portion, Garland Armstrong, identified in the transcript as a resident from the East Side of Ward 2, asked about the target completion date for the Skywalk repairs, noting concerns about ongoing construction impacts and dust. A city official responded with a completion date of "01/21/2026." The transcript reflects no further public testimony on the item. The resolution as recorded approved contract and bond and designated the bidder; the transcript does not include a construction schedule beyond the single completion-date response given at the meeting.