Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Water Supply Permitting Msa topic

No spam. Unsubscribe anytime.

MSA water-report: raw-water pump-station permitting, capacity and funding process explained

5793415 · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Board liaison reported Aug. 11 that the county's raw-water pump station is grandfathered but that upgrades will trigger new permitting for withdrawal capacity and that MSA is pursuing state and federal funding programs including FCAP.

A brief board report described recent Virginia Section American Water Works Association activity and summarized implications for the regional water system managed by the Mountain States Authority (MSA). Board members and the MSA liaison highlighted three points: the county's raw-water pump station that withdraws from the Maury River is currently grandfathered under its withdrawal permit; making upgrades (including moving facilities out of the flood plain or installing a generator) would trigger re-permitting for withdrawal capacity; and the Department of Environmental Quality's Office of Water Withdrawal may consider historic usage when establishing new permitted capacities.

The report noted the current system capacity is approximately 4 million gallons and that MSA is using about half of that now. Board members expressed concern that a new permit might limit future development if regulators base permitted capacity on recent usage rather than projected need. Staff said MSA and the central Shenandoah planning district are engaging on a regional water-supply plan and pursuing funding via the Virginia Department of Health's Financial and Construction Assistance Program (FCAP) and other commonwealth and federal funding programs; staff described past success in converting low-interest loans into loan forgiveness for certain projects.

The board heard the report as informational; no action was taken at the meeting. Staff suggested MSA and county officials will continue coordination on permit, capacity and funding matters.

Speakers quoted in this article are drawn from the meeting record and are listed below.