Yukon parks moves forward with playground upgrades and a 10-year master plan; Taylor Park pulled from immediate playground list

5793317 · August 21, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Parks staff told the board the city posted an RFP for a comprehensive 10-year parks and recreation master plan, will solicit proposals and select finalists in late September; staff also removed Taylor Park from the current playground procurement because of floodplain and related issues and extended the Bledsoe Park deadline.

Ryan, parks and recreation staff member, told the board the city has published a request for proposals to develop a comprehensive parks and recreation master plan, a first for Yukon, and that the City Council approved the plan and timeline in a recent council meeting. Staff said they reached out to 12 firms and also posted the RFP publicly to meet legal notice requirements.

Why it matters: The master plan will guide capital priorities and funding choices for the next decade, including whether to repair or replace long-serving facilities and how to prioritize playground and field investments across neighborhoods.

Staff said proposals for the master plan are due on September 15; the department plans to select three to five finalists, interview those finalists during the week of September 22–26, and ask the council to consider a recommendation at its October 7 meeting. Ryan said the plan will include community outreach (events and surveys), cost estimates for short-, mid- and long-term projects, and comparisons of staffing and operations with peer cities.

On playground procurement, Ryan said the department received more than 10 proposals for each targeted playground and that they expect to decide on three parks by the end of the week or the following Monday; Bledsoe Park proposals had an extended deadline. The parks initially considered Dickinson, Welch, Greenbelt and Taylor Park; staff removed Taylor Park from the current procurement because of floodplain concerns and will instead advance Bledsoe Park in the near term.

Staff described typical supplier lead times of "around a 10 to 12 week process" from signed agreement to installation, and estimated a likely installation window of late November to early December if agreements are signed on schedule. Ryan said the department asked firms to propose a range of play equipment and not identical fixtures across parks, to create variety in neighborhood offerings.

Discussion and direction: Board members asked that the master-plan scope include staffing comparisons, salary benchmarks and operational improvements; Ryan confirmed that staffing and comparative data with similar Oklahoma cities were included in the RFP. There were no formal votes about contracts at the meeting; the report and timeline were informational and staff will return with finalist recommendations.

Ending: The board set a tentative next meeting date of Wednesday, September 17 at 6 p.m., at which members expect to hear progress updates and may receive recommendations related to the master plan and playground agreements.