Facilities committee reports summer capital progress; Tabansy/Tappan Zee vestibule changed to transaction window
Summary
Committee notes presented to the board summarized on-schedule summer abatement and construction work across elementary, middle and high school phases, and noted a decision to install a transaction window in a high-school vestibule rather than a fixed window.
Get email alerts on the Facilities Capital Projects topic
No spam. Unsubscribe anytime.
The board received facilities committee notes reporting that summer capital work and abatement projects were largely completed on schedule across district schools and that the district revised a previous design choice for a high-school vestibule.
Why it matters: Capital progress and design decisions affect school safety, access and when spaces are ready for students and staff.
The facilities committee recapped Phase 1 work at Cottage Lane Elementary and William O. Schaefer (abatement completed ahead of schedule, data network backup on track, virtual maps and CPL issued), Phase 2 work at Tappan Zee High School (abatement completed on schedule, data network backup running ahead of schedule) and Phase 2a auditorium submittals beginning. The committee reported a late tile delivery that affected the 400 wing at Tappan Zee but said overall opening-day readiness improved from last year.
Committee notes show the Tabansy/Tappan Zee high-school administrative-suite vestibule was reviewed and the committee decided to change a previously planned fixed window to a transaction window (a window sized and configured for person-to-person transactions). The facilities committee requested cost information from the construction manager (TPG) before altering the original design. The record also shows custodial crews began work earlier than scheduled (cleaners started 08/19), and window-unit replacement and glass scheduling was planned for September after substantial completion.
The committee indicated the Tappan Zee nurses entry meets ADA requirements. Phase 3 at SOMS is planned for bid posting in late October.
Looking ahead: The committee will continue submittal reviews, finalize transaction-window costs with TPG and move Phase 3 to bid posting later in the fall; the board noted no additional committee motions at the meeting.