Council approves utility capital projects, sludge removal contract and vendor agreements
Summary
The council approved a $720,580 sludge removal contract funded with ARPA dollars, awarded a 40-by-60 utility shop building bid, discussed water-plant solar panels and approved a services agreement to support future capital project design.
Get email alerts on the Utilities Capital Projects topic
No spam. Unsubscribe anytime.
Bolivar council members approved multiple utility and capital items during the September meeting, including an ARPA-funded contract to remove sludge from lagoon Cell 1, a utility shop building contract and an agreement to use a third-party design services firm for future capital projects.
Sludge removal: The council approved a $720,580 contract to remove sludge from Lagoon Cell 1, funded with American Rescue Plan Act (ARPA) monies. The utility board had recommended the project and the council carried a motion to approve the award. The contract amount was described as below the ground budgeted amount for the full program; council members said the award had a positive recommendation from the utility board and the city’s engineers.
Utility shop building: The council opened sealed bids for a 40-by-60 utility shop and awarded the contract to Blue Steel Manufacturing (Henderson) at a total building cost of $73,706.18. Council members discussed the trade-offs between awarding a lower out-of-town bid and supporting a local contractor; the board ultimately recommended and the council moved forward with the low bid.
Solar panels and energy savings: Utility staff reported that solar panels were installed at the water plant and that technical commissioning of the inverter/software was expected the week of the meeting. Utility staff estimated the water plant’s monthly electric bill at roughly $12,000–$14,000 and said the solar installation is expected to pay for itself in about eight years and reduce operating costs going forward.
Procurement: The council approved a single bid for 8-cubic-yard dumpsters from Waste Equipment at $1,078 each (nine units; total $9,702), an item the council said fit within the procurement budget.
Project delivery services: The council also voted to enter an agreement with Performance Services to provide front-end design budgeting and value-engineering on future city projects, a process the mayor described as intended to keep projects within budget before bidding. Councilmembers asked whether the arrangement created any open-ended cost to the city; staff said Performance Services’ fees would be included in individual project budgets (similar to engineering fees) and would not trigger standalone payments outside a specific project. Council approved the agreement subject to the city attorney’s review and standard contract procedures.
YMCA project: Staff reported they have submitted plans and materials to USDA and expected an answer on appropriation approval within 30 to 60 days.
Why it matters: The approved actions allocate ARPA funding for wastewater maintenance, advance energy reduction measures at the water plant, and position the city to use a design-to-budget approach on future capital projects. Council discussion highlighted local procurement preferences and the need for attorney review of outside agreements.
Decisions taken: Sludge removal contract ($720,580) — approved; 40x60 building award to Blue Steel Manufacturing ($73,706.18) — approved; dumpster procurement ($9,702) — approved; agreement with Performance Services to provide project design-to-budget services — approved subject to contract review by the city attorney. The council also directed staff to monitor project schedules and provide updates.
Ending: Staff said they will return with contract documents and scheduling details; the sludge removal and building contracts will proceed through standard procurement and execution steps.