Board approves Reese Wholesale Storage expansion encroachment, with detention and bond conditions
Summary
Petitioner Projects Plus presented a plan to remove stone placed in the Canary regulated drain, add a dry detention basin and provide a new outlet; the county's outside engineer recommended approval subject to a 125% bond of the work within the easement and the board approved that recommendation.
Get email alerts on the Reese Wholesale Encroachment topic
No spam. Unsubscribe anytime.
Project consultant Joseph Heck of Projects Plus presented plans on Sept. 2 for Reese Wholesale Storage to address previous unpermitted stone fill in the Canary regulated drain by removing a portion of the stone, installing a dry detention basin and adding a new outlet pipe to the Canary ditch.
Heck said the city of Franklin had cited the site for improvements placed without permits and that the proposed work would remove stone from the floodway and reduce impacts to the legal drain while providing a dry detention area on-site. He described the proposed outlet and said the plan is intended to meet Franklin's and county release-rate requirements.
Surveyor Greg Cantwell told the board the site had been reviewed by the county's outside engineer, who recommended approval given the site's limitations; Cantwell recommended the same bond condition used elsewhere: 125% of the engineer's estimate for work inside the easement.
Board action: A board member moved to approve the encroachment request contingent on the suggested bonding; the motion carried.
Why it matters: The plan seeks to correct prior unpermitted work by removing fill from the floodway and replacing it with detention and a controlled outlet to the regulated drain. The board's approval is conditional on the petitioner posting the bond and meeting the other engineer-recommended conditions.
Ending: The petitioner must post the required bond and implement the detention and outlet per approved plans; the board's approval is contingent and documented in the meeting minutes.