Capital projects update: East Blas 3–4 on budget; East Blas 5 collections not yet started
Summary
District capital projects staff reported East Blas 3 and 4 are on budget and outlined construction progress across multiple schools; staff said East Blas 5 collections have not begun.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
District capital projects staff provided a quarterly update on the East Blas (SPLOST) program and other construction work at the Sept. 2 board meeting.
Key points - East Blas 3 and East Blas 4: Staff reported the programs are “in excellent budget shape” with projected costs aligning with revenues for the projects shown. The presentation included cost-versus-revenue charts and a contingency line staff said will permit reallocation as projects close.
- Cash-on-hand and contingency: Staff noted the projected cash-on-hand at the end of the projects is $0, and encouraged continued attention to cash flow and project closeout. Contingency funds, when freed as projects complete, were described as an opportunity to fund additional work.
- Project status: Construction work and demolition were described for multiple campuses (Windsor Forest, J.G. Smith, Islands, Georgetown, Hubert, Garden City, and others). Staff said interviews for design professionals were scheduled for the West Chatham K–8 athletic facility and that roofing, HVAC and turf projects continue.
- Contractor market and minority participation: Staff reported healthy contractor interest for several bids and said a minority-owned contractor participated on recent projects, which district representatives highlighted.
- East Blas 5 collections: A board member noted that, although voters approved East Blas 5, the state has not yet permitted the district to begin collecting those SPLOST (penny) proceeds; staff said no funds are available yet for E-Blas 5 projects.
Why it matters Capital projects affect school facilities and the schedule for opening improved classrooms, gyms and fields. The board’s oversight of SPLOST-funded projects shapes local construction contracts and vendor participation.
Next steps Staff said multiple projects will move to bid or construction in the coming quarter and that board representatives will receive project updates at future meetings.