Committee reviews bleacher replacement, completed bathrooms and mechanic‑shop abatement
Summary
Committee received brief status reports: new bleachers at Edinburg North are complete and hold nearly 900; a fixed‑assets bathroom renovation finished Aug. 15 (~$35,000); Dela Vina bathroom work (~$10,000) was completed to meet ADA requirements; mechanic‑shop testing found asbestos and abatement is under way.
Get email alerts on the Maintenance Improvements topic
No spam. Unsubscribe anytime.
The Facilities Committee received several shorter maintenance updates Wednesday.
Edinburg North High School: Facilities staff reported a bleacher replacement project completed the Friday before school began. Raymond (facilities) said the contractor Specialty Supply and Installation delivered bleachers at a cost of about $191,000; the installation seats a little under 900 and staff completed owner training with coaches and the principal. Committee members asked about adding lighting and a south‑side set of bleachers in the future; staff said lighting will require additional budgeting.
Fixed assets bathroom: Julie Bettis, director of maintenance, told the committee a fixed‑assets bathroom renovation finished Aug. 15 at an approximate cost of $35,000. The work included an ADA ramp, repainted parking and new handicapped spaces, replaced partitions and mirrors, and other fixture updates; Bettis said employees were advised and the facilities are returning to regular use.
Dela Vina Elementary: Bettis also reported a smaller bathroom renovation at Dela Vina that added stalls and made the space ADA compliant; she said the work cost approximately $10,000. The committee discussed reviewing older campuses, and a board member asked staff to review bathroom capacity at Barrientes (an older campus) as part of longer‑range planning.
Mechanic shop: Facilities staff said asbestos testing in the mechanic shop returned positive results; abatement procurement is underway and staff have selected a floor plan for the renovated area. Staff noted the work will include bringing the space up to ADA standards.
No formal committee votes were recorded for these informational items; staff will continue with construction closeout, training and abatement procurement and will update the board as needed.