Canterbury, Cavazos roof projects on schedule; $200,000 of savings reallocated to high‑school multipurpose storage and apron
Summary
Architects reported Canterbury roof is watertight and 80% complete, Cavazos is about 30–35% complete; roof work came in under budget and the committee agreed to use $200,000 of savings for a concrete apron and additional storage at a high school multipurpose room.
Facilities staff and project architect Charles Garcia of CG5 Architect LLC updated the committee on two roof replacement projects. Garcia said the Canterbury roof work is “watertight right now on the roof, and they're about 80% complete,” and that Cavazos Elementary’s roof is roughly 30–35% complete and progressing on schedule.
The architect reported no major change orders and told the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat