Final change order of $86,542 closes out ADA sidewalk project; funded from child-safety program
Summary
Public works staff presented change order No. 1 — a final, $86,542 increase — for the sidewalk and ADA ramp improvements contract to cover additional quantities and required alterations to meet PROWAG standards; staff said the change is funded from the child-safety fund and the contractor will complete remaining punch-list items.
Get email alerts on the Public Works topic
No spam. Unsubscribe anytime.
Public Works staff presented a final change order for the sidewalk and ADA ramp improvements project on Aug. 19. Change Order No. 1 with Jerrodin Enterprises LP increases the contract by $86,542, representing final measured quantities and additional tasks needed to meet PROWAG (Public Right‑of‑Way Accessibility Guidelines) and state inspection requirements.
Scope and cause: The project replaced or altered ramps and sidewalks at multiple school-area locations and one site along W.S. Young. Staff said some locations required curb and gutter modifications, additional sidewalk replacement, and alterations where strict PROWAG slope standards could not be met — in those cases the contractor performed approved modifications (alterations) and replaced longer sidewalk sections as required.
Funding and oversight: Staff said change order funding comes from the child-safety fund, an account intended for school-area safety infrastructure. The contractor will address punch-list items following state inspection.
Why it matters: The change order finalizes the project scope to ensure ramps and sidewalks meet federal/state accessibility guidance as implemented locally. Staff recommended council authorize execution of the final change order; the item was approved on the consent agenda.