Barnum and Norton construction on schedule; brick kiln issue and PCOs flagged for committee action

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractors reported steady progress at the new Barnum (North End) and Norton schools and presented several project change items, including contaminated soils, a masonry kiln malfunction affecting a brick blend, and upcoming purchase orders; the committee scheduled a short virtual meeting to resolve invoices and PCOs.

Construction managers reported progress on both school sites and flagged a small set of cost and schedule risks for the School Building Committee to resolve.

Site and schedule: Contractors said site work and building framing are progressing and that overall percent complete on Barnum and Norton tracks to schedule. At Barnum (North End), building percent completions were reported in the single digits to mid‑20s by building block; Norton reported comparable progress with some brickwork and CMU ahead of Barnum. Temporary power for Barnum was installed pending meter activation, and roofing and…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans