Summary

Mayor Robert Sullivan, CFO Dr. Troy Clarkson and ARPA project manager Dan Pilotta briefed the Finance Committee on ARPA and related investments totaling about $56 million, reported progress on major projects and flagged remaining maintenance needs and timelines for expenditure.

Mayor Robert Sullivan, Chief Financial Officer Dr. Troy Clarkson and ARPA project manager Dan Pilotta updated the Brockton Finance Committee on Aug. 18, 2025, about the city’s American Rescue Plan Act (ARPA) projects and related federal and county funds. The administration reported roughly $56 million in projects and discussed completion status, unspent balances and a timetable for remaining work.

Why it matters: The city used one‑time ARPA funds to finance several large capital projects—city hall HVAC and envelope work, the War Memorial renovation, a council on aging expansion, the Cosgrove Pool project, acquisition of the May Center and investments in parks and the Public Safety Building. Committee members pressed for details on remaining balances and long‑term maintenance obligations.

Dr. Clarkson provided a project‑level spreadsheet showing original ARPA obligations, amounts spent to date and remaining allocations, and explained that the total projects exceed the federal ARPA allocation because the city also received a $3 million federal earmark for the pool and a $1 million state match for the council on aging addition. He said project accounting will be posted publicly on the finance page.

Project manager Dan Pilotta described the physical work at five major ARPA sites: the War Memorial (new roof and HVAC replace steam heat with VRF systems and improved ventilation); the council on aging (fire suppression replacement, HVAC and parking lot work); Cosgrove Pool (complete pool replacement and renovated bathhouse); City Hall (roof, envelope, and phased HVAC/air‑handling upgrades providing fresh air and cooling); and parks work across the city.

Pilotta cautioned that some capital work creates ongoing maintenance obligations. On City Hall he said internal cast‑iron roof drains and rain leaders are aged and may need replacement; he urged an allocation for future maintenance to protect recent investments. Pilotta also reported that the City Hall HVAC work is phased and the building should be completed in coming months, and that the administration expects to use an additional $850,000 from county ARPA funds for new boilers.

Mayor Sullivan emphasized the administration’s intent to spend ARPA funds on long‑lasting capital projects rather than short‑term operating expenses. He said departments had requested revenue‑replacement uses for some fleet and IT upgrades and that the city planned limited revenue‑replacement expenditures under the ARPA rules.

Action: The committee voted to recommend a resolve inviting the mayor, CFO and ARPA project manager for an ARPA update; the resolve was recommended favorably to the full council. Committee members asked that the project spreadsheet and supporting documentation be posted publicly and requested a future presentation on maintenance planning for the renovated assets.

Ending: The committee endorsed the administration’s ARPA accounting and asked staff to post details online and return with maintenance and procurement plans before final project closeouts.