District reports major classroom moves and modernization progress at Cathedral City, Landau and Sunny Sands
Summary
The board received a construction update: central plant work and HVAC replacements at Cathedral City High School (ESSER funds), and classroom modernizations at Landau and Sunny Sands elementary schools funded by bonds and other sources. Staff said nearly 75 classrooms were moved over two weeks in July and projects remain on budget.
Julie Arthur, executive director of facilities planning and development, told the board on Aug. 26 that the district has advanced three major modernization projects and moved scores of classrooms over the summer to open new permanent spaces.
Arthur said Cathedral City High School Increment 1 — a central plant replacement and campus utility loop paid with federal ESSER funds — is about 99% complete and in commissioning. "That's something that this central plant can actually do on that," she said, describing new HVAC units that connect digitally to diagnostics. Increment 2 at Cathedral City includes classroom renovations and HVAC work in the 100–700 wings; staff said that portion is funded with bond proceeds and the budget for the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat