Boone County amends courthouse change order, approves reduced additional cost of $11,009.62
Summary
The board approved a reduced change order for Scandalica Construction on the courthouse renovation after staff negotiated items down from the originally proposed amount; the board recorded a roll-call vote approving the revised total.
Get email alerts on the Construction And Capital Projects topic
No spam. Unsubscribe anytime.
The Boone County Board on Aug. 28 approved amended change order No. 6 for Scandalica Construction related to the county courthouse renovation. The change order was amended at the meeting from an originally proposed $28,830 to $11,009.62 after staff negotiated scope and pricing clarifications.
Why it matters: The courthouse project is a high-profile capital renovation. Board members asked for specifics about the change orders before voting; staff and the project representative outlined discrete items covered by the amendment, including additional restroom valves, added fire-extinguisher cabinets requested by the Belvidere Fire Department, window tuckpointing to address water penetration discovered during demolition, a larger-than-allowed generator upgrade and snow guards for metal roofs.
Details presented: County project staff and contractor representatives explained the line items: PCO 41 ($1,473) for additional restroom valves; PCO 37 ($1,875) for additional fire-extinguisher cabinets requested during permit review; tuckpointing and window repairs for water infiltration; an over-allowance on the generator to increase future capacity; and snow guards for metal roofing totaling $4,707. Staff said the change-order package presented at the meeting totaled $11,962 and was adjusted to $11,009.62 for approval.
Board action: The motion to approve the amended change order was made by a board member and seconded; the board approved the amended amount by roll call. County reviewer Randy Darnell recommended approval, saying the proposed change orders were “fair, reasonable, and would recommend their approval.”
Next steps: The courthouse project will continue under the revised budget adjustments; staff indicated construction is progressing and the project remains on an extended timeline.
Ending: The board noted visible progress on exterior copper roofing during a site visit and said the interior finishes were taking shape; staff estimated substantial completion would be later in the coming year.