Harper Woods council approves three infrastructure payments tied to sewer and water projects
Summary
The council approved progress and debt payments totaling $240,232.10 for sewer rehabilitation, lead service replacement and a clean-water loan payment; members sought clarification on program distinctions and liner effectiveness.
Get email alerts on the Infrastructure Water Sewer topic
No spam. Unsubscribe anytime.
The Harper Woods City Council on March 3 approved three separate payments for ongoing sewer and water work totaling $240,232.10.
The council passed a resolution to pay Institute Form Technologies USA $5,152.10 for progress payment No. 2 (final) on the 2024 sewer rehabilitation full‑length CIPP lining project (project number 180-339). Council members then approved progress payment No. 1 of $38,205 to Super Construction LLC for the DWSRF lead water service replacement project (project number 180-331). Finally, the council approved a principal-and-interest payment of $196,875 to U.S. Bank Trust Company for the State of Michigan Clean Water Program loan.
Council members asked for more information about how the different programs interact and about the technical limits of pipe liners. During discussion, a council member asked whether lining sewer pipes would reduce the number of surface cracks and breaks. City staff responded that liners can prevent leaks but are vulnerable if a pipe shifts or is ripped by freeze–thaw movement; staff described the recent severe freeze–thaw cycle as a cause of “circular cracks” that can displace pipe and defeat a liner’s effectiveness.
Councilmembers also pressed staff for clarification on the difference between the DWSRF lead service replacement project and the larger Clean Water Program loan payment; a council member said she had expected the lead‑service work to be folded into the state revolving fund assistance and asked about expected principal forgiveness. Acting staff said they would provide the full distinction and the financing details to the entire council following the meeting.
All three resolutions passed on roll call votes. The council did not adopt additional policy changes tied to the payments at the meeting and asked staff for follow-up materials on technical and financing questions.