Council hears financing options to accelerate Santa Paula's pavement program; staff recommends pay-go but offers blended loan scenario

5764565 · June 4, 2025

Get AI-powered insights, summaries, and transcripts

Subscribe
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Advisors presented three ways to accelerate the Measure R-funded pavement program: a PAYGO five-year plan, a blended $8 million loan plus pay-go to shorten construction to ~2.5 years, or a financing-only approach; staff and council debated inflation risk versus interest cost and the need to coordinate underground utility work.

City financial advisors presented three alternatives for accelerating Santa Paula's pavement-management program using Measure R receipts: (1) pay-as-you-go (PAYGO) expanded investment to $4 million per year for five years; (2) a blended approach with an $8 million financing and $12 million PAYGO that would accelerate the program to roughly 2—2— years; and (3) a financing-only approach.

Christian Sprunger of NHA Advisors summarized the tradeoffs: option 1 minimizes interest cost but exposes the program to a longer construction horizon and therefore greater inflation risk; option 2 incurs interest costs (NHA modeled roughly $1.6 million cash-flow interest on an $8 million, 8—10-year structure) but shortens exposure to inflation and lets the city avoid the price increases that accompany multi-year construction windows. NHA's sensitivity scenarios showed that under moderate inflation (3'4%) shorter construction schedules could materially reduce total purchasing-power loss on construction budgets.

Why it matters: Council must weigh the near-term costs of carrying debt against the risk that asphalt, labor and material price inflation will raise project costs on a longer schedule. The city also must coordinate paving with anticipated water, sewer and storm-drain projects to avoid re-trenching recently paved streets and minimize rework.

Key discussion points and staff guidance: - NHA framed option 2 as a realistic compromise: a short-term (8—10-year) financing, structured likely as a lease revenue bond or a private placement, with interest fixed for the term and the possibility of drawdown financing (a line of credit) to match actual construction draws. - NHA estimated the blended option would increase nominal cash-flow cost by about $1.6 million versus PAYGO but reduce present-value purchasing-power loss compared with a longer five-year construction window, depending on inflation assumptions. - Council and staff repeatedly raised the need to coordinate paving with water and sewer master-plan work and upcoming utility rate studies; Public Works emphasized the high cost of water/sewer replacements and advised caution to avoid paving then digging later. - A number of councilmembers favored the five-year PAYGO approach to allow time for water/sewer planning and to avoid debt-service pressure on future Measure R receipts; other councilmembers and staff saw benefit in partial financing to avoid inflation and finish the work sooner.

Outcome and next steps: Council did not select a final financing path at the meeting. Staff and NHA will return with additional analysis if Council wants to pursue a partial financing (including indicative bank bids for a drawdown structure), and staff will also prepare pavement-prioritization plans that explicitly account for needed underground utility work so paving is sequenced to minimize rework.