Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Victoria County approves $835,143 runway design contract, warns temporary SkyWest disruptions
Summary
Commissioners approved a Centurion Planning and Design contract for a 30% design of Runway 13/31 and heard that an upcoming taxi project may close the runway for two to four weeks; the court also ratified a minor update to the airport executive director's employment agreement clarifying emergency management oversight.
Victoria County Commissioners Court on June 2 approved an $835,143.50 contract with Centurion Planning and Design to complete a 30% design for rehabilitation of Runway 13/31 and associated taxiway improvements at the Victoria Regional Airport and were told a taxi project could require a temporary runway closure that may disrupt SkyWest Airlines service for two to four weeks this summer.
The county judge and commissioners said the contract price has been approved by the Federal Aviation Administration. County staff told the court that parking-lot work at the airport has gone to bid and that bids are expected in mid-June. During citizens communication, airport staff warned…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat