Road and Bridge recommends ALMI Enterprises to repair main shop salt bunker for $43,237
Summary
Road and Bridge staff asked commissioners to approve a $43,237 contract with ALMI Enterprises to repair and replace the cover on the county’s main salt bunker; staff solicited three bids and said ALMI’s proposal included a protective sprayed liner intended to extend the structure’s life.
Get email alerts on the Public Works Contracts topic
No spam. Unsubscribe anytime.
Miami County Road and Bridge staff on Aug. 27 recommended the Board approve an agreement with ALMI Enterprises for repairs to the salt-storage bunker at the county’s main shop, located at 320 Seventh Street.
Public works staff said ALMI submitted the low bid at $43,237. About $32,000 of the total is for a new cover; the remaining roughly $11,250 is for repairs to the existing structure. Road and Bridge explained the contractor will clean corroded areas, install patch kits where metal has deteriorated, and spray a protective truck‑bed‑liner product about eight feet up the bars that contact concrete to reduce future corrosion. Staff said ALMI holds a MoDOT contract and has success with the spray-liner approach; staff told commissioners they expected the repairs could extend the structure’s service life 20 years or more.
Road and Bridge said they received two other quotes: a local contractor that had higher pricing and less extensive repair work, and a contractor that did not complete an on-site inspection and whose quote covered only a new cover for about $36,000. Staff said the bunker is roughly 25 years old and shows corrosion and a damaged west end; separate garage-door repairs were being quoted and are a separate item. Commissioners asked whether insurance covered the repairs; staff said this was routine age-related deterioration and not an insurance claim.
What happens next: staff requested Board approval so the contractor may proceed; no formal vote was recorded during the study session. Road and Bridge said they will inspect other bunkers at remote shops (Hillsdale and Lewisburg) and bring future budget requests as needed.
Attribution: project scope and bid comparisons were described by Road and Bridge staff during the Aug. 27 study session.