Airport runway extension bids come in within budget; city match reduced to 5 percent

5736705 · April 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Bids for the airport runway extension came in with an apparent low bidder; project cost is roughly $2.1 million in construction with the city's required match at about 5 percent (~$150,000). Staff will review bids and bring a recommendation to the council.

The committee received an update on the municipal airport runway extension: bids were opened and the apparent low bidder on the construction contract is KJU. The construction portion of the apparent low bid is approximately $2.1 million; the overall project cost includes design and construction engineering.

Staff reported that, unusually for the current funding round, the state match requirement for this grant is 5 percent rather than 10 percent, which reduces the city’s cash obligation to about $150,000. Bids are valid for 120 days while staff completes a review and prepares a council agenda item.

If the contract is awarded, staff said construction is anticipated late summer to early fall. No formal committee action was required or taken at the briefing; staff will return to the city council with a formal recommendation after final bid review.