Board approves $70,036 pay request for Front Street and Pottery Road water‑line work
Summary
The City of Washington Board of Public Works approved a $70,036 pay request covering waterline work on Front Street and Old Pottery Road; staff said the Front Street replacement is the largest recent waterline project and Old Pottery Road work connects Meadow Lake and new Don Avenue development.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The City of Washington Board of Public Works on Jan. 28 approved a $70,036 pay request to complete water‑line work on Front Street and Old Pottery Road, staff said.
Kevin, staff member, presented the pay request as a combined final payment for multiple waterline tasks, saying the Front Street replacement — from Market Street to Stafford Street — is likely the largest waterline replacement the city has had in years and that the timing is advantageous because Front Street is being repaved. “That's one of our oldest lines, highest pressure,” Kevin said.
Kevin said the same pay request also covers reinstalling a water line on Old Pottery Road under a prior agreement to extend service to Meadow Lake; the work includes installing a fire hydrant and curb stops so new Don Avenue houses can connect. Kevin noted the pay request amount matched a separate pipe purchase used for both projects.
At one point in the presentation a board member read the pay request amount aloud: “$70,036.” The board moved and seconded the payment and approved it by voice vote; no roll‑call tally appears in the meeting record.
Transcript language referenced a vendor as “core in Maine,” but the transcript did not clearly identify a firm or provide a contract number; staff said the payment is a final pay request. Kevin told the board that weather delayed immediate work and that crews planned to start Old Pottery Road work as soon as ice cleared and then move to Front Street.
Why it matters: The projects replace aging water mains, add fire protection to a subdivision and bring new development on Don Avenue into the city system; the combined $70,036 payment was described as the final pay request for the work.
Votes at a glance: Pay request motion moved, seconded and approved by voice vote; amount approved $70,036.