Poudre River master-plan effort moves to design phase; staff to study four priority areas
Summary
City staff reported completion of Phase 1 for the Poudre River Restoration Initiative Master Plan and said Phase 2 design work will focus on four study areas with additional public meetings and outreach planned; the presentation was informational and no council action was requested.
Get email alerts on the River Restoration topic
No spam. Unsubscribe anytime.
City staff updated the Greeley City Council in February 2025 on the Poudre River Restoration Initiative Master Plan, reporting completion of a Phase 1 synthesis and announcing Phase 2 design work focused on four study areas.
A presenter for the restoration initiative said the project “is rooted in the understanding that a healthy river is essential for a vibrant and healthy…community,” and described Phase 1 as a compilation of 31 prior studies, roughly 150 GIS data layers, three pop-up events, a digital survey and 21 meetings with staff and partners. The presenter said there are no final designs yet and that the session was informational only.
Why it matters: staff and partners framed the river as an ecological, recreational and economic asset that requires integrated planning to balance habitat, infrastructure, water law and private property interests across an urban corridor. The master plan principles—20 in total and available on the city’s engagement site—are intended to guide design, governance and future policy conversations across the corridor.
Details from the presentation: Phase 1 compiled data and stakeholder input and used a prioritization framework that ranges from conservation to enhancement or creation of habitat depending on existing conditions. The team identified four study areas for Phase 2 design; staff said these areas were selected based on potential ecological benefit, feasibility and community priorities, and that downtown connections and private-landowner constraints (water rights and ownership) informed the choices.
Public engagement and schedule: consultants and staff plan two public meetings in spring and summer 2025, additional outreach to a steering committee and property-owner-focused engagement. Staff indicated a mid- to late-August return to council to seek adoption of the master plan after Phase 2 if the schedule holds.
Funding and implementation: presenters said the master plan will include an actionable project list and a financial strategy noting grant opportunities and possible local funding approaches; staff emphasized the intention that the plan be implementable rather than a shelf study. No funding commitments or motions were made at the work session.
Ending: Council members asked about private-public partnerships and prioritization of downtown projects; staff said partnerships with property owners, developers and pavilion owners will be explored further during Phase 2. The presentation did not request council action at the meeting.