5520733 · April 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

At the April 4 meeting the Board of Commissioners approved a 50/50 INDOT road grant, engineering agreements for a roundabout, multiple concrete street repair contracts, a Russo Center change order and a bridge contract amendment; several property and donation actions were also approved.

The Allen County Board of Commissioners on April 4 approved a package of infrastructure and property actions including acceptance of an INDOT 50/50 local road-and-bridge matching grant for up to $1,500,000, agreements for roundabout engineering, multiple concrete-street repair contracts, a contract change order for perimeter work at the Rousseau Center and an INDOT amendment for a bridge replacement.

Bill Hartman of the Allen County Highway Department presented the Community Crossings grant award, saying the county is eligible for up to $1.5 million under the program and plans a set of resurfacing and drainage projects across northern and southern Allen County. Hartman said the package of projects has an estimated total cost a little under $3,000,000 and will be advertised for bidding in May with a planned completion in November 2025. He told the board the state program requires a 50% local match.

The board approved an agreement with Butler, Fairman & Seifert, Inc. for engineering and right-of-way services related to the Leesburg and Kramer Road roundabout not to exceed $554,555. Hartman described the Leesburg/Kramer location as the first of three planned roundabouts in the area and noted the design will include a 100-foot diameter roundabout with 12-foot truck aprons and work on large drainage culverts.

Facility maintenance director Vance Hernandez requested approval of Change Order No. 1 for the Russo Center 2023 perimeter improvements. Hernandez said Schenkel Construction performed plaza, landscaping and veneer-panel work and that while on site crews addressed settling pavers that posed a tripping hazard; the fix included leveling pavers and adding eight concrete benches. Hernandez said labor and related work totaled about $72,458 and the benches cost $33,915; after using a $50,000 contingency and accounting for earlier allocations of $8,766.45, the project left a deficit of $31,224.45, which the board approved as an increase to the contract.

The board also accepted bids from Milestone Contractors LP for two 2025 concrete-street repair projects: Oak Grove Villas and Oak Grove Extended ($884,146.28) and Carriage Cove ($434,039.54). County staff noted the two awards together total approximately $1.318 million, exceeding the department’s $1.2 million annual minimum goal for concrete repairs.

Other approvals included acceptance of a donation of two parcels from the Northwest Allen County Middle School Building Corporation valued at about $63,770 to support the Union Chapel Trail (staff said the parcels are the last needed for state funding eligibility), acceptance of a 50-foot right-of-way warranty deed from LBGBCG Parkview LP, and INDOT Amendment No. 1 to DES 2101756 increasing the bridge replacement contract for Bridge No. 24 on Cuba Road over Oberholtzer Ditch by $24,000. The INDOT bridge work is federal-aid (80/20) and will replace an existing span with a wider structure; staff said the amendment adds the appraisal cost for a required parcel.

All motions during the meeting carried by voice vote.