Allen County approves $22,828 change order and final payment for 2024 traffic striping contract
Summary
The board approved Change Order No. 1 adding $22,828.30 to the 2024 traffic striping work and accepted the project with a final contract amount of $537,238.30 to Victory Trucking and Supply Inc., doing business as 3 Rivers Barricade and Equipment Company.
Get email alerts on the Transportation Maintenance topic
No spam. Unsubscribe anytime.
The Allen County Board of Commissioners approved Change Order No. 1 to the 2024 traffic striping contract, adding $22,828.30 to cover additional roads added to the work, and accepted the project with a final contract price of $537,238.30 to Victory Trucking and Supply Inc., doing business as 3 Rivers Barricade and Equipment Company.
Highway staff explained the contract extension was used to lock unit prices and avoid rebidding, and that additional miles added through the county’s resurfacing and gravel‑to‑chip‑and‑seal program increased the quantity of striping work. “This 22,000 represents the additional roads that we added to the contract,” the presenter said.
Commissioners moved, seconded and approved the change order and project acceptance by voice vote.