Chubbuck Road landfill solar permit filed; Energy Commission warned permit review can extend months
Summary
Commissioners heard that the Chubbuck Road landfill solar project has submitted a solid-waste permit to the state Department of Environmental Services and that review timelines (about 120 days) plus potential back-and-forth could delay construction and affect bonding and incentive timing.
The Energy Commission received an update Feb. 27 on the Chubbuck Road landfill solar project: the project team has filed a solid-waste permit application with the New Hampshire Department of Environmental Services and is preparing an alteration-of-terrain (AOT) application.
Jean Walker, assistant town manager, said the DES solid-waste permit has the longest review time—about 120 days under typical schedules—and that the process…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat