Commission approves $22.3 million guaranteed maximum price for Jackie Robinson Ballpark renovation

5502532 ยท March 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The City Commission approved Amendment No. 2 to the design-build contract with Barton Milo Builders LLC for the Jackie Robinson Ballpark renovation, authorizing a guaranteed maximum price (GMP) of $22,284,087. The resolution passed 7-0.

The Daytona Beach City Commission on March 5 approved Amendment No. 2 to Contract No. 2428 with Barton Milo Builders LLC for design-build services at Jackie Robinson Ballpark, authorizing a guaranteed maximum price (GMP) of $22,284,087 for the construction segment of Phase 1.

Commissioner Reed moved the resolution and Commissioner May seconded it on the floor; the commission approved the contract amendment by voice vote, 7-0.

The resolution approves the GMP for the construction segment of phase 1 services and authorizes up to $22,284,087 to be expended for that segment. The action also approves minor contract revisions needed in association with GMP approval. No public speakers addressed the item during the meeting.

The contract amendment is described in the agenda as Amendment No. 2 to Contract No. 2428 between the city and Barton Milo Builders LLC for design-build services related to the Jackie Robinson Ballpark renovation project. The resolution provides an effective date and authorizes the expenditure noted above.

The vote record shows unanimous approval; the agenda did not list specific construction phasing dates in the discussion at the meeting. Staff indicated no speakers and no additional public testimony on the item.