Commissioners approve $35,500 change order for Fillmore Road project; change orders total 14.9% increase so far
Summary
The board approved change order number 6 for the Fillmore Road project to fund additional water-main work and hydrant relocation; the change adds $35,500 and increases total change orders on the project to about 14.9 percent.
Get email alerts on the Capital Projects Change Orders topic
No spam. Unsubscribe anytime.
The St. Joseph County Board of Commissioners approved change order number 6 on May 13 for the Fillmore Road project in the Indiana Enterprise Center area.
County staff said the change order covers additional water-main work required to relocate a fire hydrant and carries an increase of $35,500, about a 1.4% increase to the contract. The presenter said cumulative cost increases from change orders on the project total about 14.9% to date.
Commissioners asked staff why the total had reached 14.9%. Staff said recent change orders included construction of an access road to reach work areas and to allow R and L carriers and other users to access sites during construction; staff said the access road was the largest single cost among the earlier change orders. The presenter described the access road and other items as beneficial to on-site operations.
The commissioners approved change order number 6 by voice vote. The project covers Fillmore Road from Larson to the west, in the Indiana Enterprise Center area; staff did not provide a revised total contract amount during the meeting.
No additional environmental or permit issues were raised on the record during the change-order discussion.