Board awards Moab Park concrete expansion contract to low bidder for $52,500
Summary
Board of Public Works and Safety accepted the lowest responsive proposal for concrete work at Moab Park and approved R and D Construction at $52,500 pending final legal and staff review.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The Crown Point City Board of Public Works and Safety on Thursday approved awarding the Moab Park concrete expansion contract to the lowest responsive bidder, R and D Construction, at $52,500, pending final legal and staff review.
Adam Greer presented three proposals for concrete work within the fenced footprint of Moab Park: Milestone Contractors LP at $61,676; Reeth Riley at $74,935; and R and D Construction at $52,500. Greer described the work area as west of the turf and near the amphitheater stage; the concrete will create a loading area and pathways to accommodate trucks and equipment during concerts and events and to reduce recurring turf damage. Greer said the selected bid includes footings tied to a previously approved rigging truss redevelopment.
Board members asked about drainage and slope. Greer and engineering staff said the design retains a slope to the northwest so surface flow continues to the existing low area; drains near the stage will remain. The board voted to approve the low bid with the condition of final legal and engineering review.
The motion passed on a voice vote with no recorded opposition. The contract award covers only work inside the park fence line; staff said landscaping buffers will be preserved and some grass retained.