Summary

The Lawrence Redevelopment Commission approved a not-to-exceed $9,000 contract amendment with HWC to prepare and solicit bid packages for three medians on Pendleton Pike once an INDOT permit is granted.

The Lawrence Redevelopment Commission on a unanimous voice vote approved an amendment to HWC's scope of work to prepare, solicit and analyze bids for landscaping three medians on Pendleton Pike.

The amendment, described to commissioners as a not-to-exceed $9,000 hourly cap, will fund HWC's work to assemble bid packages, solicit quotes and analyze responses for the first three medians proceeding from the interstate toward Post Road. The commission's presiding officer called for the motion; a commissioner moved and a second was recorded before commissioners voted "aye." The commission directed that any resulting construction contract would return to the commission for final approval.

Why it matters: The amendment moves the project from design to procurement, enabling the city to seek contractors after the city obtains the required Indiana Department of Transportation permit. Commission discussion clarified the procurement pathway: staff said the commission intends to keep individual bid packages below the $150,000 threshold cited in the discussion so the solicitation can proceed by quotes rather than a full formal bidding process, and that a seven-day open period is typical for those quote solicitations.

Interim Director Greg Goodnight summarized the amendment's scope and schedule and said HWC would prepare alternate bid options to provide cost comparisons for commissioners. Councilor Brown disclosed a prior business relationship with HWC, saying, "In the interest of full disclosure, they are my clients, but I did not participate in the selection of them for any of that work." The commission recorded that disclosure on the public record before voting.

Commissioners were told HWC has previously worked on the Trades District design and is working on the Record Street reclassification; staff emphasized that the bid-award recommendation will include responsiveness and responsibility analyses and will be returned to the commission for award.

Next steps: Staff will seek the INDOT permit; once issued HWC may proceed with solicitation under the amended scope and bring bid recommendations back to the commission for final contract award.