The Muncie Redevelopment Commission approved a not-to-exceed $37,773.08 payment to replace damaged downtown planters with resin units and keep seasonal plantings, after a staff presentation and questions about installation and maintenance.

The Muncie Redevelopment Commission on March 20 approved a not-to-exceed $37,773.08 expenditure to replace damaged decorative planters in the downtown core and maintain seasonal plantings.

The measure won unanimous roll-call approval after a presentation from a project representative who said the limestone planters installed about 10 years ago are frequently damaged and that the recommended resin planters include water-reserve features to reduce maintenance. "They have agreed to continue to plant them four times a year," the presenter said, referring to the Community Enhancement Project, which currently handles downtown plantings.

The request covered replacement of up to 24 planters, though staff said the final purchase might be 20 planters with two spares; the presenter noted the per-unit price in the materials as $15.75 each and described the new planters as heavier and more resistant to damage. Commissioners asked whether the city street department would handle installation and whether the project was separate from the annual $80,000 the commission provides to the Muncie Downtown Development Partnership; staff said this request would be a city project and that street department/install arrangements remain to be finalized.

Commissioners and staff emphasized timing: replacing the planters before the spring planting season would avoid missing a planting cycle. The project representative asked for the not-to-exceed authorization to allow ordering and coordination before the commission's next meeting.

The commission approved the motion, and staff said they will report back on final counts and any savings.

Funding and implementation details beyond the not-to-exceed authorization — including final installer, storage for extra units, and exact number of planters purchased — were left to staff follow-up.