Kokomo board signs off on $67,730 pay estimate and releases escrow for Hofer Street work
Summary
The board approved pay estimate number 4 for Hofer Street reconstruction and released $129,199.65 held in escrow to E and B Paving LLC after approving a contract modification.
Get email alerts on the Street Reconstruction topic
No spam. Unsubscribe anytime.
The City of Kokomo Board of Public Works and Safety on May 14 approved pay estimate number 4 for the Hofer Street reconstruction project and authorized release of escrow funds to the contractor.
Darren Metz, traffic systems manager, presented quantity sheets for pay estimate number 4 for E and B Paving LLC. Metz said pay estimate number 4 covers construction quantities completed from Dec. 14, 2024, through May 2 and totals $67,730.55 with no retainage.
He also said contract modification agreement number 1 increased the original contract by $38,620.59, resulting in an adjusted contract amount of $2,651,723.59. Metz recommended approval of pay estimate number 4 and release of $129,199.65 held in escrow to E and B Paving LLC; the board approved both motions by voice vote.
Background: the project is in active construction with quantities periodically submitted by the contractor and verified by the engineering department. The release of escrow funds was part of the staff recommendation.