Board approves $205,539 payment and $2,660 contract change for northeast water main project

5436066 · May 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved pay estimate number 6 and contract modification number 2 for the Northeast Water Main Extension Phase 2, covering unseen utility relocations and associated cost adjustments.

The City of Kokomo Board of Public Works and Safety on May 14 approved pay estimate number 6 and contract modification number 2 for the Northeast Water Main Extension Phase 2.

John Pike, director of engineering, said modification number 2 covers relocation and repair of unseen utilities that affected the planned elevation of the water main and increases the contract by $2,660.30. He presented pay estimate number 6 for E.S. Wagner Company covering work and stored materials completed to April 30; the pay estimate request subtotal, with percentages applied, produced a payment recommendation of $205,539.35 to the contractor.

Pike stated the original contract amount was $4,210,569, which has been revised to $4,231,904.02 by contract modifications number 1 and 2. “Therefore, I am recommending the Board of Public Works and Safety approve payslip number 6 in the amount of $205,539.35 to ES Wagner Company,” he said.

Board members moved and seconded the payments and the contract modification; both motions carried by voice vote. The transcript records no roll-call vote for these actions.

Background: Donahue Associates is the consulting engineer that reviewed the contractor’s submitted quantities. The board’s approval authorizes payment for completed work and documents the utility-related change to the contract.