Kokomo board approves contract tweaks and $252,000 payment for northeast sanitary sewer work
Summary
The City of Kokomo Board of Public Works and Safety approved two contract modifications and a pay application tied to the Northeast sanitary sewer extension project, increasing the contract and authorizing payment and retainage.
Get email alerts on the Sanitary Sewer Extension topic
No spam. Unsubscribe anytime.
The City of Kokomo Board of Public Works and Safety on May 14 approved contract modifications 2 and 3 and a pay application for work on the Northeast Sanitary Sewer Extension Phase 2.
John Pike, director of engineering, told the board that contract modification number 2 restores curb-and-gutter work that had been removed from an earlier change order and specifies the city will pay the contractor $65 per foot to install curb and gutter when city crews were unavailable, rather than the $200-per-foot figure removed in modification 1. He said modification number 2 increases the contract by $6,500 and modification number 3 — for a newly installed drive at the Hagerman development that required additional full-depth granular backfill — increases the contract by $3,840. “I recommend the Board of Public Works and Safety approve contract modifications number 2 and number 3,” Pike said.
At the same meeting Pike presented pay application number 4 for Atlas Excavating Inc. He said the project’s original contract was $988,120 and subsequent modifications raised the amount to about $1,327,598, and that modifications 2 and 3 add another $10,340 making the adjusted contract $1,637,938. Pike recommended approval of application number 4 in the amount of $252,323.05 with $13,280.16 placed into a retainage account.
A motion to approve the contract modifications passed by voice vote; a second motion approved pay application number 4 and the retainage. The board did not state a roll-call tally during the public record for these items.
Background: the project consultant is Donahue Associates; Atlas Excavating Inc provided the installed quantities used to prepare the payment request. The board’s approval allows the contractor to be paid for work and establishes the additional charges to the contract for curb work and the Hagerman development drive.
Less critical details: the board handled these items in its regular meeting; no separate public hearing was recorded.