Change order reduces contract amount for High Plains use center renovations
Summary
A change order presented to the county deducts $72,518.43 from the Western Builders contract for the High Plains use center renovation, lowering the contract from $3,540,107.05 to $3,467,588.62; the court approved the change order 5–0.
Get email alerts on the Capital Project Change Order topic
No spam. Unsubscribe anytime.
Randall County Commissioners Court approved May 13 a change order for the High Plains use center renovations that reduces the county’s contract with Western Builders by $72,518.43.
Staff said the change order reflects contractor credits, including a deduction of $71,394 for an owner contingency item and a smaller deduction of $1,124.43 for construction manager contingency. The net effect reduces the original contract amount from $3,540,107.05 to $3,467,588.62.
Staff explained the project experienced delays unrelated to the county’s decision, notably a lock manufacturer acquisition and pricing changes that affected final costs. ‘‘In the process of it being sold, the vendor ... changed the price ... they reviewed the cost, and that is why you see that there is a better price that is in here than what had originally been expected,’’ a county presenter said.
SMP Architects and Western Builders approved the change order; the court voted 5–0 to accept it. The county will execute the change order and finalize contract records.
Why it matters: The change order reduces the county’s contracted liability and finalizes adjustments tied to construction contingencies and vendor pricing changes encountered during the project.
Next steps: Staff will sign the change order and process final invoicing and contract closeout paperwork.