White Plains staff requests funds for fire station repairs, street resurfacing, rink cooling tower and traffic poles

4089410 · March 31, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff presented multiple capital project funding requests including $76,000 more for Fire Station 2 structural design, $2.5 million bonded portion for street reconstruction, $300,000 for Ebersol rink cooling tower replacement and design for two traffic light poles.

Commissioner (title given in the transcript as Commissioner Mignogni) presented four capital items to the White Plains Common Council on March 31 that would be included in forthcoming capital appropriations or bond-funded work.

Fire Station 2: Mignogni said engineers found “significant structural deficiencies” after an initial $150,000 appropriation for investigative work and design; she requested an additional $76,000 for testing and structural repair design. Fire Station 2 is the station located near the White Plains Train Station on Ferris Avenue.

Miscellaneous street reconstruction (FY2025): Mignogni requested $2,500,000 as the bonded portion of a $4.3 million capital resurfacing and sidewalk project that funds resurfacing, curb and ramp replacements and related work. She said additional funding is expected from New York State Department of Transportation grant programs and that the city would likely return in June to request that state funding once approved.

Ebersol ice rink cooling tower: Mignogni requested $300,000 to replace the rink’s cooling tower — the part of the refrigeration system that prevents overheating — after leaks were discovered. Council members asked whether replacing the cooling tower would address fogging on plexiglass; staff said that fogging is due to outdoor weather conditions and that the cooling tower replacement would not resolve that issue.

Traffic light poles: Mignogni described two separate accidents in the past year that destroyed traffic poles at Hamilton & Cottage and Fisher & Bank. The request is for design and construction of replacements; staff explained the high cost arises from significant foundation and structural work required for the cantilevered poles and that the city attempts to recover costs from responsible parties’ insurance where possible.

Council members asked clarifying questions about locations, the expected lifespan of equipment, and whether traffic-camera or third-party equipment would be affected by replacements; staff said Fisher & Bank definitely had no additional technology attached and were unsure about Hamilton & Cottage. No formal capital appropriations votes were recorded in the transcript during this meeting; these were funding requests and design approvals presented by staff.