West transmission pipeline about 30% installed; tunneling nears completion

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff updated the Utilities Committee on May 13 that the West Transmission pipeline project has roughly a mile of pipe installed in Segment 1 and about 4,500 feet installed in Segment 2, with overall pipe-in-ground progress around 30%; the final tunneling run is nearing breakthrough.

Corey Gray of Sunwater Utilities Engineering updated the Utilities Committee on the West Transmission pipeline progress on May 13, reporting that about a mile (5,000 feet) of pipe is installed in the southern half (Segment 1) and 4,500 feet is installed in Segment 2.

Gray said about 84% of the pipeline material has been received on site and that the…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans