Abrams Academy renovation design on track; $1.89 million budgeted, bids planned before March

3849092 · February 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

School staff reported that construction documents for Abrams Academy are near completion and the total project budget is about $1,892,230. The board was told bidding will occur if bids align with the budget and construction would occur over the summer.

Project consultants updated the School Board on planned renovations at Abrams Academy and presented a project budget of $1,892,230 for classroom, restroom and accessibility work.

The consultant, Mr. Bauer, told the board construction documents are nearly complete and that the team expects to go to bid before March. The budget covers renovation of seven classrooms, five toilet rooms, the student‑entry/reception area and three offices. If bids come in below budget, three items would be considered as add alternates: an exterior brick ramp to replace the existing metal ramp, four small‑group classrooms at the east end, and a portion of the main corridor work.

Mr. Bauer said the design includes upgraded HVAC, lighting, finishes and technology. “We feel comfortable that what we're showing here is within the project budget,” he told the board, and he described a construction window that would begin after Memorial Day and run through July so work could be completed before the school year starts.

Why it matters: Abrams Academy serves smaller class sizes and alternative programming; the renovation will create appropriately sized instructional spaces and improve bathrooms, offices and access. The board will consider bids and a contract if the competitive process yields prices that fit the established budget.

Next step: Staff said construction documents will be finalized this month and the division will solicit bids. If the bids are within budget, staff will request authorization to award a contract and issue a notice to proceed so materials can be on site before summer work begins.

Ending: The board heard the update and expects a bid report at a future meeting.