Votes at a glance: Council approves vehicle purchases, Dry Fork Greenway change order, Army Corps sewer agreement and records destruction
Summary
On April 7 the council approved two vehicle purchases, a construction change order on the Dry Fork Greenway, an agreement with the Department of the Army for sewer-main work and an ordinance authorizing destruction of specified municipal records; all votes passed unanimously.
Get email alerts on the Votes topic
No spam. Unsubscribe anytime.
The Excelsior Springs City Council approved multiple resolutions and ordinances on April 7. The actions below list what council approved, the vote and key details drawn from staff presentations.
Resolution 1560 — Purchase of 2024 Ford F-550 truck with dump body for the Water Department: Approved, roll call vote unanimous. Public Works Director Chad Birdsall reported the vehicle is a 2024 one-and-a-half-ton 4x4 cab-chassis with dump body purchased from Olathe Commercial Sales at a municipal price of $92,392, within the department's $95,000 budget; the truck will replace a 2006 Ford F-1150 (144,443 miles) and be sold at auction later.
Resolution 1561 — Purchase of 2025 GMC 1500 pickup for the Pollution Department: Approved, roll call vote unanimous. Birdsall presented the low bid from Roberts Robertson (Robertson Chevrolet Buick GMC) for $43,008.56; the vehicle is a 2025 model used as a loaner with 2,312 miles and is within the Pollution Department’s 2025 budgeted amount of $50,000.
Resolution 1562 — Change Order #1 with Mega KC Corporation for the Dry Fork Greenway project: Approved, roll call vote unanimous. Change Order #1 adds pavement and other items: replacing 1,761 square yards of asphalt with 8-inch concrete ($101.53/sq yd), installing a fire hydrant and valve assembly ($11,300), foundation stabilization under a reinforced concrete culvert (158 sq yd at $111.18/sq yd) and a slab barrier tie-in ($2,732.72). The change order totals $125,865.49, increasing the contract from $3,446,468.25 to $3,572,333.34 and leaving approximately $192,115.26 available for additional change orders.
Ordinance 25-04-01 — Agreement with the Department of the Army for design and construction assistance on sewer-main improvements: Approved (second reading), roll call vote unanimous. Chad Birdsall said the federal contribution under the agreement is $1,925,000 (75%) with a city match of $641,666.67 (25%), for a total project cost of $2,566,666.67. The work targets rehabilitation and lining of existing sewer mains in neighborhoods including Wilson Acres, Glenwood/Wildwood/Lynnwood area, Gulf Hill Drive, East Valley Park, Forest Drive, Bell Drive and Old Time Drive. McClure Engineering will serve as design engineer; a separate agreement with McClure was announced as forthcoming.
Ordinance 25-04-03 — Authorization to destroy certain municipal records: Approved (second reading), roll call vote unanimous. City Manager Molly McGovern told the council the list follows the Secretary of State’s retention guidelines; staff plan to hold on-site shredding in May and indicated which departments’ records meet retention schedules.
Motion to close the regular session and go into a closed session pursuant to RSMo §610.021(1) and §610.021(2): Approved, roll call vote unanimous. The council closed the regular session at 6:34 p.m.
All roll-call votes recorded at the meeting showed support from Councilman Saint John, Councilman McGovern, Councilman Rennie, Mayor Pro Tem Speer and Mayor Spahn.