Council approves change order increasing Drive Fort Greenway contract to $3.6 million
Summary
The council approved Change Order No. 2 with Mega KC Corporation for the Drive Fort Greenway project, adjusting pipe materials and headwall elevations and increasing the contract by $32,367.18 to a new total of $3,604,700.92; remaining contingency from the original grant allocation was noted.
Get email alerts on the Greenway Construction topic
No spam. Unsubscribe anytime.
The Excelsior Springs City Council on May 5 approved Resolution No. 1568, authorizing Change Order No. 2 to the contract with Mega KC Corporation for the Drive Fort Greenway project.
Public Works Director Chad Birdsong presented three items in the change order: (1) revisions to reinforced-concrete box culvert headwall elevations ($6,937.70), (2) substitution of 8-inch ductile-iron class 52 pipe for a planned PVC creek crossing ($15,635.48), and (3) an asphalt pavement unit-price adjustment tied to a prior reduction in asphalt quantity (net increase $9,794). Birdsong presented the original contract price and prior change orders: original Mega KC contract $3,440,468.25; Change Order No. 1 $125,008.49; after that the contract stood at $3,572,333.74. Change Order No. 2 increased the contract by $32,367.18, bringing the new contract total to $3,604,700.92. Birdsong said $159,748.08 remained available for additional change orders within the original grant allocation.
Councilmembers had no substantive questions, and the resolution passed on unanimous roll-call vote (Rennie, McGovern, Speer, Mayor Pro Tem Saint John, Mayor Mark Spahn voted yes).
Why it matters: The change order updates necessary structural items and pipe materials for the Drive Fort Greenway project and modestly increases the contract total. Staff noted remaining contingency funds from the grant allocation.
Action taken
- Resolution: 1568 — Approve Change Order No. 2 with Mega KC Corporation for the Drive Fort Greenway project. - Vote: unanimous in favor (Rennie: yes; McGovern: yes; Speer: yes; Mayor Pro Tem Saint John: yes; Mayor Spahn: yes).