Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater Pay Request topic

No spam. Unsubscribe anytime.

Council approves $388,880.31 pay request for South Side Wastewater Treatment Plant work

3839588 · May 7, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved pay request No. 23 from Heritage Construction LLC for $388,880.31 for work at the South Side Wastewater Treatment Plant; staff reported the contract is adjusted to $41,012,657.85 and the project is about 90% time complete and 64% paid.

The Mount Pleasant City Council voted unanimously to approve pay request No. 23 from Heritage Construction LLC in the amount of $388,880.31 for work at the South Side Wastewater Treatment Plant. City staff said the payment covers equipment installation at the headworks and aeration basin, backfill around the effluent lift station, and electrical components.

At presentation, staff reported the adjusted contract value is $41,012,657.85, completed contract cost to date is $29,986,710.86, percent of time complete is 90%, and percent of money complete is 64%. Staff also said recent work included installation of screw pumps and training by the vendor Evoqua on the plant's oil system.

Councilman Redburn moved the payment and Councilman Corbell seconded; the motion passed unanimously.