County approves $7.3 million road resurfacing and ADA program; will pave about 12.6 miles

3802120 · March 25, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board awarded a $7,308,612.74 contract to Schifano Construction for the 2024 road resurfacing and ADA compliance program covering approximately 12.6 miles of county roads; the award came in about 10% below engineer's estimate.

Somerset County approved a $7.3 million contract to repave county roads and upgrade Americans with Disabilities Act curb ramps across multiple locations.

Resolution 25‑721 awards a contract to Schifano Construction Corp. of Middlesex, N.J., for the 2024 road resurfacing and ADA compliance program, not to exceed $7,308,612.74. County staff said seven bids were received and the low bid came in about 10% below the engineer’s estimate of $8,130,269. The program will repave roughly 12.6 miles of county roadway and includes ramp upgrades and traffic signal work as part of the contract.

Presenters noted some curb ramps require small easements from adjacent properties for reconstruction and that the county will coordinate easement acquisition where needed. For one shared‑service item noted earlier in the meeting, the county will install two rapid rectangular flashing beacons in Hillsborough as part of the paving project; Hillsborough will maintain those beacons after installation.

The resolution was approved by roll call at the Jan. 12 meeting. County staff said work will begin once the contract is executed and funding is certified.

Why it matters: the project affects local travel and accessibility on several county roads and implements ADA curb‑ramp upgrades required as part of resurfacing work.

Votes at a glance: Resolution 25‑721 — award to Schifano Construction, not to exceed $7,308,612.74; approved by roll call (yes votes recorded at meeting).